Rug production capacity and lead time planning

Plan a container programme in four blocks: sampling (5 to 20 days, cost credited against the order), approval, bulk production (8 to 16 weeks) and sea transit (about 4 to 10 days to Jebel Ali up to about 35 to 55 days to Canada, port to port). Two illustrative plans below show 12 and 20 weeks to ready-at-port; your quote confirms real dates.

Last updated: 31 October 2026

The stages and their ranges

Timeline building blocks
StageRangeNotes
Sampling, including lab dips5 to 20 daysCost credited against the order
Sample approval and purchase orderYour decision timeAllow for one revision round
Bulk production8 to 16 weeksFrom sample approval; confirmed on your quote
Export documents and loadingConfirmed on your quoteFOB Nhava Sheva is usual
Sea transit, port to portSee table belowApproximate; clearance and delivery extra

Sea transit ranges from Nhava Sheva

Approximate port-to-port transit (checked 30 October 2026)
RegionDays
Gulf (Jebel Ali)4 to 10
Australia (Sydney, Melbourne), low confidence18 to 30
Europe (Rotterdam, Hamburg, Antwerp)20 to 35
UK (London Gateway, Felixstowe)22 to 35
US East and Gulf25 to 40
US West30 to 45, low confidence
Canada (Halifax, Montreal), low confidence35 to 55

These are planning ranges, not promises. Cape routing, transshipment, congestion and blank sailings extend them. Use the sea freight transit finder and fit cartons with the container loading calculator.

Two illustrative plans

Illustrative only. These plans combine our stated ranges to show how a programme can be laid out. They are not commitments; your quote confirms the real dates.

Illustrative 12-week plan (short end of bulk)
WeeksStage
1 to 3Sampling and lab dips (within the 5 to 20 day range)
4Sample approval and purchase order, 50% advance
5 to 12Bulk production, 8 weeks
After week 12Export documents, loading at Nhava Sheva, then sea transit
Illustrative 20-week plan (long end of bulk)
WeeksStage
1 to 3Sampling and lab dips
4Sample approval and purchase order, 50% advance
5 to 20Bulk production, 16 weeks
After week 20Export documents, loading, then sea transit

In both plans, add sea transit for your region from the table above, plus destination clearance and delivery, to reach your warehouse date. The 50% balance is due before dispatch.

Capacity: what to ask

  • Ask how many pieces of your construction and size can be made in your window, and in how many shipments. Shipments can be split on wholesale orders; we confirm quantities per order on your quote.
  • Mixed orders and several designs can be planned together; ask how sizes and materials affect timing.
  • Plan buffer weeks for revisions, festival and holiday periods, and booking cut-offs.

Related reading

See how to order, the sampling process, how to read a quote, rug trade data and the country guides, for example the EU and the UAE.

Plan your first container

Send your design, size and estimated quantity. We reply within two business days, usually within one. Minimum order: 1 piece. Sampling cost is credited against your order. Payment: 50% advance, 50% before dispatch.

Get a quote on WhatsApp

Buyer questions

Planning lead times: your questions

How long does a rug order take from sample to shipping?

Sampling takes 5 to 20 days and bulk production 8 to 16 weeks, then export loading. Our illustrative plans show 12 and 20 weeks to ready-at-port; your quote confirms dates.

Is the 12 week plan guaranteed?

No. It is an illustration using the short end of our bulk range. Real timing is confirmed on your quote.

Does bulk start before the sample is approved?

No. Bulk follows the approved sample.

How long is sea freight?

It depends on the region, from about 4 to 10 days to Jebel Ali to about 35 to 55 days to Canada, port to port. See the table above and the transit finder.

Can I split an order into several shipments?

Yes. Shipments can be split on wholesale orders. Tell us the delivery sequence you need when you enquire.

What can delay a programme?

Late sample approval, design changes after approval, booking cut-offs, transshipment and port congestion.

When is payment due?

50% advance and 50% before dispatch.